Bearing inspection
A bearing does not fail on a calendar. It fails on a curve that starts weeks before, and the curve is measurable. The monthly look is replaced by a reading with a threshold.
- Condition that replaces the interval
- Vibration velocity above the machine's baseline by 20% or above the ISO 20816 zone boundary, or bearing housing temperature above baseline by 10 C
- Reading that proves it
- Vibration velocity (mm/s RMS) and bearing temperature per bearing
- Evidence an auditor accepts
- Vibration trend per bearing with the baseline and alarm thresholds recorded, and the work order raised when the alarm fired
- First move
- Take a baseline reading on every bearing on the list while it is healthy; without a baseline there is nothing to compare against.
What it is evidence for
Clause references from a human-verified corpus licensed to Maintenance Log Converter. A clause marked reference is named, not reproduced.
Calendar tasks a monitored condition could replace ISO 55001:2014 9.1 · ISO 55001:2014 8.1 · ISO 55001:2014 6.2.2 · ISO 55001:2014 8.2 · ISO 55001:2014 10.3 · ISO 45001:2018 8.1.3
ISO 55001:2014 9.1 Monitoring, measurement, analysis and evaluationThe organization determines what needs to be monitored and measured, the methods for monitoring, measurement, analysis and evaluation to ensure valid results, when monitoring and measuring is performed, and when results are analysed and evaluated. It evaluates and reports on asset performance, asset management performa...
ISO 55001:2014 8.1 Operational planning and controlThe organization plans, implements and controls the processes needed to meet requirements and to implement the actions determined in planning, including the actions to address risks and opportunities and the asset management plans. It establishes criteria for the processes, implements control in accordance with the cri...
ISO 55001:2014 6.2.2 Planning to achieve asset management objectivesThe organization integrates the planning to achieve asset management objectives with other organizational planning, including financial, human resources and other support functions. It establishes, documents and maintains asset management plans that define the decision-making method and criteria, the processes and meth...
ISO 55001:2014 8.2 Management of changeRisks associated with any planned change, permanent or temporary, that can have an impact on achieving the asset management objectives are assessed before the change is implemented, and the organization ensures such risks are managed in accordance with 6.1 and 6.2.2. The organization controls planned changes and review...
ISO 55001:2014 10.3 Continual improvementThe organization continually improves the suitability, adequacy and effectiveness of its asset management and its asset management system.
ISO 45001:2018 8.1.3 Management of changeThe organization establishes processes for the implementation and control of planned temporary and permanent changes that impact OH&S performance, including new products, services and processes or changes to existing ones (workplace locations and surroundings, work organization, working conditions, equipment, workforce...
Do this for your whole schedule