Pressure vessel and boiler statutory examination
Corrosion is a rate, and a thickness trend tells you the rate. The examination interval is still the law, but the trend tells the competent person where to look.
What does a pressure vessel and boiler statutory examination involve?
Pressure vessel and boiler statutory examination checks: wall thickness at marked points, safety valve set pressure and lift, pressure and temperature history, weld or corrosion findings. Observed by competent person examination under the written scheme; ultrasonic thickness gauge for the trend. Examination intervals are set by the written scheme under the Pressure Systems Safety Regulations in the UK, AS/NZS 3788 in-service inspection in Australia, and state boiler and pressure vessel laws (NBIC) in the US.
- Condition that replaces the interval
- Partly. Wall thickness by ultrasonic testing and safety valve lift can be trended, and pressure and temperature are already monitored; the examination under the written scheme stays on its statutory interval.
- Reading that proves it
- Wall thickness at marked points, safety valve set pressure and lift, pressure and temperature history, weld or corrosion findings
- Why the interval stays
- Examination intervals are set by the written scheme under the Pressure Systems Safety Regulations in the UK, AS/NZS 3788 in-service inspection in Australia, and state boiler and pressure vessel laws (NBIC) in the US.
- Evidence an auditor accepts
- Examination report per vessel with the next examination date, and the thickness readings by location
- First move
- Mark the thickness measurement points on the vessel so every reading is at the same spot; a trend from moving points is noise.
What it is evidence for
Clause references from the published standards text. A clause marked reference is named, not reproduced.
Statutory intervals that must stay on the calendar ISO 45001:2018 9.1.2 · ISO 45001:2018 6.1.2.1 · ISO 45001:2018 8.1.2 · ISO 45001:2018 8.1.4.2 · ISO 55001:2014 4.2 · ISO 55001:2014 8.1
ISO 45001:2018 9.1.2 Evaluation of complianceThe organization sets up, runs and keeps processes for evaluating whether it complies with legal and other requirements. It decides how often and by what methods compliance is evaluated, carries out the evaluation and acts where needed, keeps up its knowledge and understanding of where it stands on compliance, and reta...
ISO 45001:2018 6.1.2.1 Hazard identificationSet up, run and keep a hazard identification process that is continuous and looks ahead. The process shall take into account: social factors and the way work is organized; activities that are routine and those that are not; incidents that have happened before; possible emergencies; people, including workers, contractor...
ISO 45001:2018 8.1.2 Eliminating hazards and reducing OH&S risksThe organization sets up, runs and keeps processes for removing hazards and lowering OH&S risks by working down the hierarchy of controls: first remove the hazard; next replace it with processes, operations, materials or equipment that are less hazardous; then apply engineering controls and reorganize the work; then ap...
ISO 45001:2018 8.1.4.2 ContractorsThe organization aligns its procurement processes with its contractors so that hazards are identified and the OH&S risks are assessed and controlled where they come from three sources: contractor activities and operations that affect the organization; the organization's own activities and operations that affect contrac...
ISO 55001:2014 4.2 Understanding the needs and expectations of stakeholdersThe organization identifies which stakeholders are relevant to its system for managing assets, and what they require and expect from asset management; it sets the criteria it will use to make asset management decisions; and it identifies what stakeholders require in the way of recorded financial and non-financial infor...
ISO 55001:2014 8.1 Operational planning and controlThe organization plans, carries out and controls the processes needed to satisfy requirements and to deliver three things: the asset management plans set out under 6.2, the actions on risks and opportunities decided under 6.1, and the preventive and corrective actions decided under clauses 10.1 and 10.2. It does so by ...
Do this for your whole schedule