Fire hydrant and hose reel test
A hydrant that has not been flowed for years is a hydrant nobody knows works. The interval is the code; keep it.
What does a fire hydrant and hose reel test involve?
Fire hydrant and hose reel test checks: flow and pressure at the outlet, hose condition, reel unwinds and shuts off cleanly. Observed by annual flow test by a contractor; six-monthly visual. Test intervals are set by AS 1851, BS 9990 and NFPA 25.
- Condition that replaces the interval
- None that replaces the interval. Riser pressure can be supervised continuously.
- Reading that proves it
- Flow and pressure at the outlet, hose condition, reel unwinds and shuts off cleanly
- Why the interval stays
- Test intervals are set by AS 1851, BS 9990 and NFPA 25.
- Evidence an auditor accepts
- Annual test certificate with flow and pressure per outlet, and the six-monthly visual record
- First move
- Record the flow figure, not a tick. A falling flow year on year is a supply problem you want to know about early.
What it is evidence for
Clause references from the published standards text. A clause marked reference is named, not reproduced.
Statutory intervals that must stay on the calendar ISO 45001:2018 9.1.2 · ISO 45001:2018 6.1.2.1 · ISO 45001:2018 8.1.2 · ISO 45001:2018 8.1.4.2 · ISO 55001:2014 4.2 · ISO 55001:2014 8.1
ISO 45001:2018 9.1.2 Evaluation of complianceThe organization sets up, runs and keeps processes for evaluating whether it complies with legal and other requirements. It decides how often and by what methods compliance is evaluated, carries out the evaluation and acts where needed, keeps up its knowledge and understanding of where it stands on compliance, and reta...
ISO 45001:2018 6.1.2.1 Hazard identificationSet up, run and keep a hazard identification process that is continuous and looks ahead. The process shall take into account: social factors and the way work is organized; activities that are routine and those that are not; incidents that have happened before; possible emergencies; people, including workers, contractor...
ISO 45001:2018 8.1.2 Eliminating hazards and reducing OH&S risksThe organization sets up, runs and keeps processes for removing hazards and lowering OH&S risks by working down the hierarchy of controls: first remove the hazard; next replace it with processes, operations, materials or equipment that are less hazardous; then apply engineering controls and reorganize the work; then ap...
ISO 45001:2018 8.1.4.2 ContractorsThe organization aligns its procurement processes with its contractors so that hazards are identified and the OH&S risks are assessed and controlled where they come from three sources: contractor activities and operations that affect the organization; the organization's own activities and operations that affect contrac...
ISO 55001:2014 4.2 Understanding the needs and expectations of stakeholdersThe organization identifies which stakeholders are relevant to its system for managing assets, and what they require and expect from asset management; it sets the criteria it will use to make asset management decisions; and it identifies what stakeholders require in the way of recorded financial and non-financial infor...
ISO 55001:2014 8.1 Operational planning and controlThe organization plans, carries out and controls the processes needed to satisfy requirements and to deliver three things: the asset management plans set out under 6.2, the actions on risks and opportunities decided under 6.1, and the preventive and corrective actions decided under clauses 10.1 and 10.2. It does so by ...
Do this for your whole schedule
Paste your maintenance schedule or log and get this classification for every line at once, with the findings, the overdue items and the clauses the register is evidence for. First 15 items free, no account.
Convert my scheduleFixed suppression system inspection (gas, foam, kitchen) · Fire evacuation drill